Windytop Primary (Copy)
EstimatingCindy & Michael Holland96 Windy Top, Christiana Pa 17509
- Project start
- Projected completion
- Dec 2, 2026
- Project lifetime
- 408 days292 working
- Total cost
- $0
- Progress
- 0%
Drag the handle in the Move column to reorder (drop onto a subtask to nest it, or onto a section heading to move it there). Hover a row to trace its chain.
| Move | # | Task | Status | Days | Start | End | Predecessors | Successors | Cost | Running cost | Actions |
|---|---|---|---|---|---|---|---|---|---|---|---|
0/5 done | 13 day span | 13 | Jan 21 | Feb 6 | Through day 109 | $0 | $0 | ||||
1 | Not started | 4 | Jan 26 | — | 3 | $0 | $0 | ||||
2 | Not started | Jan 26 | — | — | $ | $0 | |||||
3 | Not started | Jan 28 | 1 | 4 | $ | $0 | |||||
4 | Not started | Jan 30 | 3 | 5 | $ | $0 | |||||
5 | Not started | Feb 4 | 4 | 6 | $ | $0 | |||||
6 | Not started | Feb 6 | 5 | 7 | $ | $0 | |||||
0/6 done | 43 day span | 63 | Feb 9 | Apr 8 | Through day 170 | $0 | $0 | ||||
7 | Not started | Feb 20 | 6 | 8 | $ | $0 | |||||
8 | Not started | Mar 13 | 7 | 9, 10, 11 | $ | $0 | |||||
9 | Not started | Mar 27 | 8 | 12, 22 | $ | $0 | |||||
10 | Not started | Mar 27 | 8 | 16 | $ | $0 | |||||
11 | Not started | Apr 3 | 8 | 12, 16 | $ | $0 | |||||
12 | Not started | Apr 8 | 11, 9 | 13 | $ | $0 | |||||
0/3 done | 23 day span | 26 | Apr 9 | May 11 | Through day 203 | $0 | $0 | ||||
13 | Not started | Apr 13 | 12 | 14, 15 | $ | $0 | |||||
14 | Not started | May 11 | 13 | 16 | $ | $0 | |||||
15 | Not started | Apr 16 | 13 | 21 | $ | $0 | |||||
0/5 done | 37 day span | 36 | May 12 | Jul 1 | Through day 254 | $0 | $0 | ||||
16 | Not started | May 14 | 11, 10, 14 | 17 | $ | $0 | |||||
17 | Not started | May 15 | 16 | 18 | $ | $0 | |||||
18 | Not started | Jun 19 | 17 | 19 | $ | $0 | |||||
19 | Not started | Jun 30 | 18 | 20 | $ | $0 | |||||
20 | Not started | Jul 1 | 19 | 23 | $ | $0 | |||||
0/4 done | 56 day span | 16 | Apr 17 | Jul 3 | Through day 256 | $0 | $0 | ||||
21 | Not started | Apr 30 | 15 | 22, 23 | $ | $0 | |||||
22 | Not started | May 5 | 21, 9 | 52 | $ | $0 | |||||
23 | Not started | Jul 1 | 20, 21 | 24 | $ | $0 | |||||
24 | Not started | Jul 3 | 23 | 25 | $ | $0 | |||||
0/4 done | 14 day span | 14 | Jul 6 | Jul 23 | Through day 276 | $0 | $0 | ||||
25 | Not started | Jul 10 | 24 | 26 | $ | $0 | |||||
26 | Not started | Jul 14 | 25 | 27 | $ | $0 | |||||
27 | Not started | Jul 20 | 26 | 28 | $ | $0 | |||||
28 | Not started | Jul 23 | 27 | 29 | $ | $0 | |||||
0/4 done | 10 day span | 10 | Jul 24 | Aug 6 | Through day 290 | $0 | $0 | ||||
29 | Not started | Jul 29 | 28 | 30 | $ | $0 | |||||
30 | Not started | Jul 30 | 29 | 31 | $ | $0 | |||||
31 | Not started | Aug 3 | 30 | 32 | $ | $0 | |||||
32 | Not started | Aug 6 | 31 | 33 | $ | $0 | |||||
0/6 done | 23 day span | 23 | Aug 7 | Sep 8 | Through day 323 | $0 | $0 | ||||
33 | Not started | Aug 12 | 32 | 34 | $ | $0 | |||||
34 | Not started | Aug 21 | 33 | 35 | $ | $0 | |||||
35 | Not started | Aug 28 | 34 | 36 | $ | $0 | |||||
36 | Not started | Sep 2 | 35 | 37, 39 | $ | $0 | |||||
37 | Not started | Sep 7 | 36 | 38, 40 | $ | $0 | |||||
38 | Not started | Sep 8 | 37 | 42, 43, 44 | $ | $0 | |||||
0/3 done | 15 day span | 17 | Sep 3 | Sep 23 | Through day 338 | $0 | $0 | ||||
39 | Not started | Sep 9 | 36 | 46 | $ | $0 | |||||
40 | Not started | Sep 9 | 37 | 41 | $ | $0 | |||||
41 | Not started | Sep 23 | 40 | 63 | $ | $0 | |||||
0/5 done | 9 day span | 19 | Sep 9 | Sep 21 | Through day 338 | $0 | $0 | ||||
42 | Not started | Sep 15 | 38 | 46 | $ | $0 | |||||
43 | Not started | Sep 15 | 38 | 45, 46 | $ | $0 | |||||
44 | Not started | Sep 15 | 38 | 46 | $ | $0 | |||||
45 | Not started | Sep 17 | 43 | 46 | $ | $0 | |||||
46 | Not started | Sep 21 | 42, 43, 44, 45, 39 | 47 | $ | $0 | |||||
0/4 done | 15 day span | 15 | Sep 22 | Oct 12 | Through day 357 | $0 | $0 | ||||
47 | Not started | Sep 24 | 46 | 48 | $ | $0 | |||||
48 | Not started | Sep 25 | 47 | 49 | $ | $0 | |||||
49 | Not started | Oct 2 | 48 | 50 | $ | $0 | |||||
50 | Not started | Oct 12 | 49 | 51 | $ | $0 | |||||
0/8 done | 19 day span | 42 | Oct 13 | Nov 6 | Through day 382 | $0 | $0 | ||||
51 | Not started | Oct 14 | 50 | 52, 56 | $ | $0 | |||||
52 | Not started | Oct 21 | 51, 22 | 53, 55 | $ | $0 | |||||
53 | Not started | Nov 4 | 52 | 54 | $ | $0 | |||||
54 | Not started | Nov 6 | 53 | 59, 62 | $ | $0 | |||||
55 | Not started | Oct 30 | 52 | 59 | $ | $0 | |||||
56 | Not started | Oct 21 | 51 | 57 | $ | $0 | |||||
57 | Not started | Oct 28 | 56 | 58 | $ | $0 | |||||
58 | Not started | Nov 5 | 57 | 60, 61 | $ | $0 | |||||
0/4 done | 4 day span | 9 | Nov 6 | Nov 11 | Through day 387 | $0 | $0 | ||||
59 | Not started | Nov 11 | 54, 55 | 63 | $ | $0 | |||||
60 | Not started | Nov 10 | 58 | 63 | $ | $0 | |||||
61 | Not started | Nov 9 | 58 | 63 | $ | $0 | |||||
62 | Not started | Nov 9 | 54 | 63 | $ | $0 | |||||
0/7 done | 15 day span | 15 | Nov 12 | Dec 2 | Through day 408 | $0 | $0 | ||||
63 | Not started | Nov 13 | 59, 60, 61, 62, 41 | 64, 65 | $ | $0 | |||||
64 | Not started | Nov 16 | 63 | 68 | $ | $0 | |||||
65 | Not started | Nov 20 | 63 | 66 | $ | $0 | |||||
66 | Not started | Nov 24 | 65 | 67 | $ | $0 | |||||
67 | Not started | Nov 27 | 66 | 68 | $ | $0 | |||||
68 | Not started | Nov 30 | 67, 64 | 69 | $ | $0 | |||||
69 | Not started | Dec 2 | 68 | — | $ | $0 | |||||
| Project total0/68 tasks complete | 292 work days | 408 | Oct 21 | Dec 2 | calendar days | $0 | |||||