All projectsOpen in planner 



Now: Estimating & Pre-Design
Windytop Primary (Copy)
96 Windy Top, Christiana Pa 17509
Project timeline
Oct 21, 2025 to Dec 2, 2026 · 292 work days · $0
0/68 done
Today
- Estimating & Pre-Design, current, Jan 21 to Feb 6
- Design, upcoming, Feb 9 to Apr 8
- Approvals, upcoming, Apr 9 to May 11
- Permitting, upcoming, May 12 to Jul 1
- Pre-Construction, upcoming, Apr 17 to Jul 3
- Demolition & Site Work, upcoming, Jul 6 to Jul 23
- Foundation, upcoming, Jul 24 to Aug 6
- Framing, upcoming, Aug 7 to Sep 8
- Exterior Envelope, upcoming, Sep 3 to Sep 23
- Rough-Ins (MEP), upcoming, Sep 9 to Sep 21
- Insulation & Drywall, upcoming, Sep 22 to Oct 12
- Interior Finishes, upcoming, Oct 13 to Nov 6
- MEP Trim & Fixtures, upcoming, Nov 6 to Nov 11
- Inspections & Closeout, upcoming, Nov 12 to Dec 2
- Estimating & Pre-DesignJan 21
- DesignFeb 9
- ApprovalsApr 9
- PermittingMay 12
- Pre-ConstructionApr 17
- Demolition & Site WorkJul 6
- FoundationJul 24
- FramingAug 7
- Exterior EnvelopeSep 3
- Rough-Ins (MEP)Sep 9
- Insulation & DrywallSep 22
- Interior FinishesOct 13
- MEP Trim & FixturesNov 6
- Inspections & CloseoutNov 12
Current milestone
Estimating & Pre-Design
Jan 21 – Feb 6 · 0/5 tasks done · $0
Active task: Kickoff call (Not started) · Next: Site visit & existing conditions

Project planner
Schedule, dependencies, costs, Gantt and calendar.
List · Gantt · Calendar

Design selections
Add the design app link under Project details in the planner to open it from here.
5 active rooms · Kitchen, Primary Bath, Front Facade…

Documents & drawings
Drawings, proposals and contracts, and inspiration photos.
0 drawings · 0 contracts · 0 inspiration

Buyout & bids
Bid sets by scope, tied to planner tasks.
No scopes yet
Targets
- Target budget
- Not set
- Scheduled cost
- $0
- Target start
- Not set
- Scheduled start
- Oct 21, 2025
- Projected completion
- Dec 2, 2026
Customer
- Cindy & Michael Holland
- 96 Windy Top, Christiana Pa 17509
- 484-574-9104
- 22cindylou@gmail.com