Project overview

Hale Residence

Estimating

Dana & Marcus Hale148 Willow Creek Rd

Project start
Projected completion
Aug 27, 2027
Project lifetime
311 days223 working
Total cost
$0
Progress
0%

Drag the handle in the Move column to reorder (drop onto a subtask to nest it, or onto a section heading to move it there). Hover a row to trace its chain.

Move#TaskStatusDaysStartEndPredecessorsSuccessorsCostRunning costActions
0/5 done
10 day span10Oct 21Nov 3Through day 14$0$0
1
Not started
Oct 21—2$$0
2
Not started
Oct 2313$$0
3
Not started
Oct 2724$$0
4
Not started
Oct 3035$$0
5
Not started
Nov 346$$0
0/6 done
43 day span63Nov 4Jan 1Through day 73$0$0
6
Not started
Nov 1757$$0
7
Not started
Dec 868, 9, 10$$0
8
Not started
Dec 22711, 21$$0
9
Not started
Dec 22715$$0
10
Not started
Dec 29711, 15$$0
11
Not started
Jan 110, 812$$0
0/3 done
23 day span26Jan 4Feb 3Through day 106$0$0
12
Not started
Jan 61113, 14$$0
13
Not started
Feb 31215$$0
14
Not started
Jan 111220$$0
0/5 done
37 day span36Feb 4Mar 26Through day 157$0$0
15
Not started
Feb 810, 9, 1316$$0
16
Not started
Feb 91517$$0
17
Not started
Mar 161618$$0
18
Not started
Mar 251719$$0
19
Not started
Mar 261822$$0
0/4 done
56 day span16Jan 12Mar 30Through day 161$0$0
20
Not started
Jan 251421, 22$$0
21
Not started
Jan 2820, 851$$0
22
Not started
Mar 2619, 2023$$0
23
Not started
Mar 302224$$0
0/4 done
14 day span14Mar 31Apr 19Through day 181$0$0
24
Not started
Apr 62325$$0
25
Not started
Apr 82426$$0
26
Not started
Apr 142527$$0
27
Not started
Apr 192628$$0
0/4 done
10 day span10Apr 20May 3Through day 195$0$0
28
Not started
Apr 232729$$0
29
Not started
Apr 262830$$0
30
Not started
Apr 282931$$0
31
Not started
May 33032$$0
0/6 done
23 day span23May 4Jun 3Through day 226$0$0
32
Not started
May 73133$$0
33
Not started
May 183234$$0
34
Not started
May 253335$$0
35
Not started
May 283436, 38$$0
36
Not started
Jun 23537, 39$$0
37
Not started
Jun 33641, 42, 43$$0
0/3 done
15 day span17May 31Jun 18Through day 241$0$0
38
Not started
Jun 43545$$0
39
Not started
Jun 43640$$0
40
Not started
Jun 183962$$0
0/5 done
9 day span19Jun 4Jun 16Through day 241$0$0
41
Not started
Jun 103745$$0
42
Not started
Jun 103744, 45$$0
43
Not started
Jun 103745$$0
44
Not started
Jun 144245$$0
45
Not started
Jun 1641, 42, 43, 44, 3846$$0
0/4 done
15 day span15Jun 17Jul 7Through day 260$0$0
46
Not started
Jun 214547$$0
47
Not started
Jun 224648$$0
48
Not started
Jun 294749$$0
49
Not started
Jul 74850$$0
0/8 done
19 day span42Jul 8Aug 3Through day 287$0$0
50
Not started
Jul 94951, 55$$0
51
Not started
Jul 1650, 2152, 54$$0
52
Not started
Jul 305153$$0
53
Not started
Aug 35258, 61$$0
54
Not started
Jul 275158$$0
55
Not started
Jul 165056$$0
56
Not started
Jul 235557$$0
57
Not started
Aug 25659, 60$$0
0/4 done
4 day span9Aug 3Aug 6Through day 290$0$0
58
Not started
Aug 653, 5462$$0
59
Not started
Aug 55762$$0
60
Not started
Aug 45762$$0
61
Not started
Aug 45362$$0
0/7 done
15 day span15Aug 9Aug 27Through day 311$0$0
62
Not started
Aug 1058, 59, 60, 61, 4063, 64$$0
63
Not started
Aug 116267$$0
64
Not started
Aug 176265$$0
65
Not started
Aug 196466$$0
66
Not started
Aug 246567$$0
67
Not started
Aug 2566, 6368$$0
68
Not started
Aug 2767—$$0
Project total0/68 tasks complete223 work days311Oct 21Aug 27calendar days$0